Just an update with school returning next week.
Currently we are scheduled to finish the final concrete pour on the speed table end of next week (Friday 05/02), so the 3-way temporary traffic lights will need to remain in place through both long weekends to allow it time to cure.
Removal of the 3 way traffic lights is planned for Wednesday 10 February.